Construction Technology For Tensioned Trusses In Sports Stadium Projects

The roof of a stadium project consists of 10 bays of tension chord trusses with a height of 15.1 m and a truss span of 149.7 m x 141.6 m. The construction steps of the tension chord trusses are mainly introduced, and finite element calculation analysis and on-site monitoring are carried out for various working conditions in the construction process to ensure safe, reliable and fine quality of the steel roof construction.

If you’re interested in sports stadiums or the construction of sports arenas, check out more of our blog – Sports Arena

Construction Technology For Tensioned Trusses In Sports Stadium Projects04

Project Overview

A stadium project is a large span space prestressed cable truss structure with a vector height of 25.3m, a transverse length of 239.8m and a longitudinal length of 141.6m. With a total construction area of 72,010m2, it is a Grade A stadium with a capacity of 9,842 seats. The structure includes the roof of the gymnasium, the roof of the exhibition hall and the enclosure of the gymnasium.

Introduction of the tension string truss

The gymnasium consists of three major parts: ring joist, tension chord joist and radial joist. The roof prestressed steel structure consists of 10 bays of tension chord trusses, consisting of upper chord stiffeners, lower chord cables and the braces between them, the upper chord is an inverted triangular truss and the lower chord cables are double cables with cold-cast anchors. The ten-bay truss has different spans and under the same cable equivalent pre-tensioning (1700KN), the cable force varies greatly, which poses higher requirements on how to organise the construction.

In this project, advanced finite element software such as Ansys and Midas/Gen were used to carry out shape finding analysis and construction simulation calculations for the structure. BEAM188 beam unit was used for the truss members and beam members, two end hinged rod units were used for the braces, Link10 units were used for the tensioning cables and Link10 units were used for the tyre frame which were only subjected to compression. At the same time, the tensioning points, cable force monitoring points and strain gauges of the main load-bearing members during the overall tensioning of the ropes are arranged to give full consideration to the overall construction scheme of the structure, so that the final geometry and internal force distribution of the structure will match the design state after the construction and tensioning of the structure in the zero state is completed.Construction Technology For Tensioned Trusses In Sports Stadium Projects

Construction techniques for tensioned trusses

Selection of construction machinery

A stadium is divided into 4,553 hoisting units, of which 1,443 are in the stadium. By analyzing the lifting capacity of the representative steel lifting units and lifting machinery in this project, one 120-ton automobile crane, one 100-ton crawler crane and two QTZ-63 tower cranes were finally selected as the main construction machinery.

Joist fabrication

The I-beam frame is made of I-beam, consisting of columns, supports and positioning blocks and movable bolts, with adjustable supports on the bull leg part of the frame. When assembling the trusses, a gap is set at the disconnecting surface to leave space for welding, so that the welders can carry out the welding on the temporary platform when welding under the butt joint.

Before fabrication, each tension chord truss is numbered, and each section of truss with different types and sizes of bars is physically placed according to the design deepening drawings. Before setting up, firstly, pad the trestle according to the elevation and axis of the segmental points of the tension chord beam so that the elevation basically reaches the design position, and then make fine adjustment after setting up. When in position, attention is paid to the control of the gap and elevation of the interface, and the position of the segmental points is basically at the centre of the frame. After adjustment and alignment, welding is carried out and the welded joints are polished to a smooth transition. During the fabrication process, in order to ensure that the curvature of the tension chord beam in its original state is in accordance with the design, a longitude and latitude meter and level were used on site to accurately locate the truss assembly process to meet the design requirements.

As the lifting members are similar in form and the tyre frame can be recycled, 6 pairs of assembled tyre frames were set up. Two sets of assembled tyre frames are set up inside the site and one 120-tonne vehicle crane is arranged for docking of steel members; four sets of assembled tyre frames are set up outside the site and one 100-tonne crawler crane is arranged for docking of steel members.

Temporary support frame fabrication and installation

Considering the large span of single joist, in order to facilitate construction and temporary load-bearing, temporary bracing frames are set up at the segmental points of each joist, each bracing frame is made of two round steel pipes of 350mm in diameter and 8mm in wall thickness, which are connected and fixed with ∟50×5 angles in the middle. A climbing ladder is set on the temporary support frame and an operating platform is set at the top.

The temporary support frame was lifted to the design position using a 100 tonne crawler crane, the foundation was compacted and the bottom was padded with a 200mm thick steel plate, which was fixed with four cable ropes after lifting into position. A level was used to guide the elevation to the temporary support frame for subsequent installation of the joist.

Lifting and assembling of tension trusses

The construction sequence of the tensioned truss is from both sides to the middle, and the tensioned truss is lifted in four sections per bay, using a 120 tonne vehicle crane and a 100 tonne crawler crane to travel within the span, and laying steel roadbed boxes at the crane travel and lifting stations. At the same time, the QTZ-63 tower crane on site was used to cooperate in the lifting.

In order to ensure that the joist will not be destabilized out of plane and to guarantee the safety of the joist lifting, the tension chord joist is lifted in four points. After the tension chord joist is lifted into position, it is corrected in time according to the measured positioning axis at the top of the support frame by using the hand chain hoist and the interface part is temporarily fixed with the support frame and the interface is welded.

During lifting, removable movable lugs are installed on the top chord of the joist. This not only reduces the workload and material consumption during the fabrication of the joist, but also eliminates the need to cut off the joist after hoisting, which reduces the work process and speeds up the construction process and avoids the possible damage to the coating layer caused by the wire rope tying method of hoisting.

After the first joist is fixed, the second joist is lifted, positioned and reinforced, and the support system between the joists is connected in time. When the two joists and the intermediate bracing system and purlins are all connected and installed, the next joist will be lifted into position after checking that there are no safety hazards in the details.Construction Technology For Tensioned Trusses In Sports Stadium Projects

Installation and tensioning of prestressing cables

The steel cable is made of twisted steel strand with a high strength steel wire with an extruded double protective layer, the tensile strength of the single steel wire of 7mm diameter is not less than 1670MPa, the yield strength is not less than 1410MPa and the tensile modulus of elasticity (E) of the steel cable is not less than 1.9×105MPa.

During construction, the ground numbered braces are lifted one by one with a crane or manual hoist, and the nodes on the braces are connected to the steel structure. Multiple hoists are used to lift the cables and connect them to the clamps at the lower end of the spars. The position of the clamps to the cables is determined according to the markings on the surface of the cable skin and the clamps are installed.

There are 10 ties in this project. According to the construction organisation plan and the actual situation of the structural form, it is difficult to tension these ties simultaneously and they need to be tensioned in batches. Considering the symmetry of the structure, the cables were divided into 5 batches, the number of cables in the same batch was 2, and the batch tensioning sequence was symmetrical from both ends to the middle. In order to ensure synchronisation of tensioning, the same batch was tensioned in five stages as follows: 0% → 25% → 50% → 75% → 90% → 100%.

Due to the insurmountable errors in the processing and installation of the steel structure, the tensioning control uses the double control principle of controlling the force and deformation of the cable, in the single tensioning of the graded tensioning process, the first four levels are based on controlling the deformation and the last level is based on controlling the force.

Tensioning process monitoring

The pre-tensioning process is a dynamic process of structural state change. The actual structural state differs from the analytical model due to errors in the installation of the steel structure, errors in the fabrication, installation and tensioning of the cables, analysis errors and environmental influences. Therefore, it is important to monitor the pre-stressing process of the cable construction to compare the difference between the theoretical analysis value and the actual structural response, so as to immediately grasp the structural state of each key construction stage and ensure that the whole process of cable construction is in a controllable state to ensure the structural safety of the construction process.

From the above analysis, it can be seen that with the construction process, the maximum vertical deformation of the structure and the equivalent force of the steel structure are constantly changing, the maximum vertical deformation of the structure during the construction process is 63.9 mm, which is similar to the design quasi-state deformation value of 64.3 mm; the maximum axial stress is 133.8 MPa, which is very little different from the design quasi-state maximum stress value of 123 MPa and meets the requirements.

The large span of the gymnasium tension chord truss structure of this stadium project requires high construction accuracy and is difficult to construct. Simulation calculations were carried out for the whole construction process, a scientific and feasible construction plan was formulated, and good results were obtained through strict process measures and technical management means, while valuable construction experience was accumulated, which is an important reference value for the design and construction of related projects in the future.

Leave a Reply

Your email address will not be published.